Project Detail #PRD/DK/21/JUL/0001

Vessel
: PATRIA (TUG)
Start Date
: 01 Jun 2021
End Date
: 10 Jun 2021
Status
: RUN
Scheduled
: -
Breakdown
:
Created By
: user
Approved By
: 01 Jun 2021 (admin)
Rejected By
: 01 Jun 2021 (admin)
Notes
: Perbaikan rutin bulanan
Survey Type (Docking Only)
: SPECIAL SURVEY 1

Docking Progress #PRD/DK/21/JUL/0001

Vessel
: PATRIA (TUG)
Name
: Docking Tugboat PATRIA 1
Start Date
: 01 Jun 2021
End Date
: 10 Jun 2021
Actual Start Date
: 02 Jun 2021
Latest End Plan
: 11 Jun 2021
Actual End Date
:
Status
: RUN
Budget
: 10.000
Owner Surveyor
: Fajar Riyadi
Project Manager
: Samal R. Adiyasa ( 13121003 )
Shipyard
: Batola Shipyard

Additional Information

Item & Timesheet List
: View
Item Docking List
: View
Docking Progress (WBS)
: View
Monitoring Weather
: View
Work Order
: View
.